CCI dismisses complaint over SECI solar tender – Power Peak Digest

Author: PPD Team Date: April 20, 2026
The Competition Commission of India (CCI) has closed proceedings against Adani Green Energy, Azure Power, and the Solar Energy Corporation of India (SECI) over alleged anti-competitive practices linked to the 7 GW solar manufacturing-linked tender. In an order dated April 16, 2026, the Commission said it found no prima facie evidence of any contravention under the Competition Act, 2002.
The complaint had alleged that the Request for Selection (RfS) documents issued by SECI in 2019 were structured to benefit large bidders, particularly Adani Enterprises and its subsidiaries, while limiting opportunities for smaller participants. It was also alleged that Azure Power India Private Ltd. acted as a proxy bidder with the intention of later transferring awarded capacity to the Adani Group. The CCI said these claims were not supported by evidence.
In its 19-page order, the Commission said the tender structure, which linked solar power purchase agreements (PPAs) with domestic manufacturing commitments, aligned with government policy goals to strengthen local manufacturing and reduce import dependence.
On claims of market dominance, the Commission noted that India’s power generation market includes multiple segments such as coal, solar, wind, hydro, and nuclear, with strong participation from public and private sector companies including NTPC, Tata Power, and JSW Energy. It said Adani Group did not appear to hold a dominant position in the broader power generation market.
The CCI also examined objections to the tender design. It said a procurer such as SECI has the authority to define technical specifications and eligibility conditions based on procurement needs. It added that the “Green Shoe Option,” which enabled additional capacity allocation, had been directed by the Ministry of New and Renewable Energy (MNRE) and did not breach tariff-based competitive bidding norms.
SECI told the Commission that it functioned as an intermediary procurer and that tariff discovery, including the e-reverse auction, was carried out transparently under the Electricity Act, 2003. It also said Azure Power later surrendered capacity because of commercial constraints, and that subsequent reallocations were completed through legal processes in consultation with distribution companies (DISCOMs) to help meet Renewable Purchase Obligations (RPOs).
The order also addressed references made to a United States Department of Justice indictment involving alleged bribery and fraud against certain executives. The Commission said such allegations fall outside the scope of the Competition Act, 2002, and are separate legal issues.
The case was closed under Section 26(2) of the Act. The original 2019 tender sought development of 7 GW of Inter State Transmission System (ISTS)-connected solar photovoltaic (PV) power plants linked with 2 GW per annum of solar manufacturing capacity covering ingots, wafers, cells, and modules. Following the reverse auction, Letters of Award were issued to Adani Green Energy and Azure Power at a tariff of Rs 2.92/kWh.
The featured photograph is for representation only.
Author: PPD Team Date: October 28, 2024 Larsen & Toubro (L&T) has secured a ‘significant’ contract, estimated between Rs 10 billion and Rs 25 billion, to implement advanced welding technologies for the ITER Organisation’s nuclear fusion project, the world’s largest, located in Cadarache, Southern France. L&T will focus on critical technologies for assembling ports and complex components within the ITER Tokamak’s vacuum vessel. ITER, the International Thermonuclear Experimental Reactor, is a large-scale scientific collaboration aiming…
Read More L&T wins order from ITER for advanced nuclear fusion project in France
Author: PPD Team Date: January 24, 2025 CleanMax has secured a long-term credit facility of AED 99 million from Hong Kong and Shanghai Banking Corporation (HSBC) to develop and finance its onsite solar portfolio in the UAE. The facility will support the installation of 92 solar assets across industrial facilities, malls, schools, and universities. Additionally, the financing includes an uncommitted accordion of AED 37 million for future projects, in line with the UAE’s Net Zero…
Read More CleanMax secures financing to develop solar projects in UAE
Author: PPD Team Date: July 21, 2025 The Ministry of Power has released detailed procedures for allocating coal linkages to power generators under the Revised SHAKTI Policy 2025. The guidelines cover both notified price and auction-based allocations, applying to Central and State GENCOs as well as private players.  The Revised SHAKTI Policy was cleared by the Cabinet Committee on Economic Affairs (CCEA) in May 2025. It lays out two key windows for coal linkage. Approved…
Read More Power Ministry finalizes dual-window coal allocation rules under Revised SHAKTI Policy 2025
Author: PPD Team Date: March 4, 2025 The Vietnam National Petroleum Group (Petrolimex) has signed a memorandum of understanding (MoU) with the Asian Development Bank (ADB) to promote energy transition in Vietnam.  Under the agreement, ADB will help Petrolimex assess its investment portfolio and develop cleaner energy strategies. This partnership aligns with Vietnam’s low-carbon goals and ADB’s 2023-26 strategy focused on governance, green economy transition, and private sector growth. Petrolimex, which controls 50% of Vietnam’s…
Read More Petrolimex and ADB partner to support Vietnam’s energy transition
Author: PPD Team Date: December 18, 2025 GE Vernova T&D India Limited announced on 17 December 2025 that it has received a Letter of Award from Power Grid Corporation of India Limited (PGCIL) for the refurbishment of the 2 x 500 MW high voltage direct current (HVDC) Chandrapur back to back link. The project is a key interconnection between the Northern and Southern regions of India. The contract awarded by the domestic public sector utility…
Read More GE Vernova wins PGCIL order for Chandrapur HVDC upgrade
Author: PPD Team Date: January 3, 2025 The US Nuclear Regulatory Commission (NRC) has approved the renewal of Xcel Energy’s Monticello nuclear plant operating licence, extending its operations until 2050, pending state regulator approval. The plant is a key component of Xcel Energy’s strategy to achieve 100% carbon-free electricity. It currently powers over 500,000 homes annually in the Upper Midwest. Xcel Energy CEO Bob Frenzel highlighted that nuclear energy will be crucial for meeting growing…
Read More US NRC approves licence extension for Xcel Energy’s Monticello nuclear plant
Your email address will not be published. Required fields are marked *






Subscribe To Our Newsletter
Contact Us
info@powerpeakdigest.com
© 2026 Power Peak Digest. All rights reserved.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply