Rooftop solar projects risk losing ALMM-II exemption due to DISCOM delays: MNRE – Power Peak Digest

The Ministry of New and Renewable Energy (MNRE) has advised distribution companies (DISCOMs) and other relevant authorities to ensure the timely inspection and commissioning of rooftop solar photovoltaic (PV) projects ahead of the upcoming Approved List of Models and Manufacturers (ALMM)-II requirement for solar cells.
In an office memorandum dated July 28, 2025, MNRE amended the implementation guidelines for ALMM applicable to solar cells. Under the revised framework, net-metering projects and open access renewable energy power projects commissioned on or after June 1, 2026, will be required to use solar PV modules listed under ALMM List-I and solar PV cells listed under ALMM List-II.
Projects commissioned before June 1, 2026, will remain exempt from the requirement to use solar PV cells from ALMM List-II, provided they are otherwise required to use ALMM-listed modules.
According to the Ministry, representations have been received highlighting delays in inspection and issuance of commissioning certificates by DISCOMs and other authorities. Such delays could affect rooftop solar projects that have already been installed, or are expected to be installed well before May 31, 2026, causing them to miss the June 1, 2026 deadline and become non-compliant with ALMM-II requirements.
To address the issue, MNRE has advised all DISCOMs, electricity departments, State Nodal Agencies (SNAs), and Chief Electrical Inspectors to Government (CEIG) offices in states and union territories to facilitate timely inspection and commissioning of eligible rooftop solar projects.
The Ministry stated that the communication has been issued with the approval of the competent authority.
The directive comes amid rapid growth in rooftop solar installations under programmes such as the Pradhan Mantri Surya Ghar Muft Bijli Yojana. With the ALMM-II compliance deadline approaching, timely commissioning has become important for developers and consumers seeking to avoid the near-term cost and supply challenges associated with domestically manufactured solar cells.
The featured photograph is for representation only.
The World Bank has approved a $134 million operation to support the green hydrogen strategy of the Pecém Industrial and Port Complex Company (CIPP) and the Government of Ceará. Located in Northeastern Brazil, CIPP is one of the country’s most advanced logistics and industrial zones and is emerging as a key site for green hydrogen…
Read More World Bank approves $134 million for green hydrogen hub in Brazil
Rajasthan Chief Minister Bhajan Lal Sharma has approved the allocation of 4,000 hectares in Bodana village, Jaisalmer district, to the Rajasthan Solar Park Development Company for establishing a 2,000 MW solar power project.  This initiative aligns with the state’s commitment to advancing renewable energy and supporting clean energy goals.
Read More Rajasthan allocates 4,000 hectares for 2,000 MW solar project
Greenzo Energy has introduced the “Un Wheel,” a 100% indigenous 1 MW alkaline electrolyzer stack designed for green hydrogen production.  Built by Indian scientists and engineers, the stack is tailored to operate effectively across diverse Indian climates, from -20°C to 60°C, with a 20-year lifespan.  It generates hydrogen at 30 bar pressure, removing the need…
Read More Greenzo Energy launches ‘Un Wheel,’ India’s first 1 MW alkaline electrolyzer stack
Suzlon Energy has introduced a new leadership structure aligned with its “Suzlon 2.0” strategy, appointing Ajay Kapur as Group Chief Executive Officer (CEO) and elevating J.P. Chalasani to the newly created Group Executive Council (GEC). The board approved the changes at its meeting on February 24, 2026. The company has set up the GEC as…
Read More Suzlon appoints Ajay Kapur as Group CEO, forms GEC
AHAsolar Technologies Limited has received a work order worth Rs 1.65 million from Hindustan Petroleum Corporation Limited (HPCL). The order was awarded on June 19, 2025. The assignment covers the preparation of detailed feasibility reports (DFR) and project management consultancy (PMC) services for solar power projects in Rajasthan and Uttar Pradesh. The scope also includes…
Read More AHAsolar wins Rs 1.65 million consultancy order for solar projects
Rail Vikas Nigam Limited (RVNL) is planning to develop a 300 MW wind-solar hybrid power project with an energy storage system (ESS) in India.  The project is estimated to cost Rs 15 billion. RVNL is exploring potential locations for the project in Bihar, Jharkhand, or Karnataka.  The company will oversee infrastructure development, including transmission systems,…
Read More RVNL plans 300 MW wind-solar hybrid project with energy storage
Your email address will not be published. Required fields are marked *






Subscribe To Our Newsletter
Contact Us
info@powerpeakdigest.com
© 2026 Power Peak Digest. All rights reserved.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply