MPC Energy Solutions’ solar plant in Guatemala enters testing and commissioning phase – TradingView

Key takeaways:
Amsterdam / Oslo – 15 June 2026 – MPC Energy Solutions NV (“MPCES”, “The Company”) today announced that its 66.1 MWp San Patricio solar photovoltaic (PV) plant in Guatemala has secured its final permit and has entered the testing and commissioning phase. The testing will start in the coming days and is then expected to take approximately two weeks. Following successful completion of the testing phase, the plant is anticipated to receive its Commercial Operation Date (COD) certificate during the month of July. Consequently, MPCES revised its timeline for starting operations from the originally guided second quarter of 2026 into the third quarter of 2026.
MPCES will be able to sell the energy generated during the testing phase and period until official COD through the spot market. Reaching COD will mark a key milestone for the San Patricio project and also represents a critical step toward the closing of the planned sale of the asset.
As a result of the delay into the third quarter, additional debt service payments, on-site staff commitments and operational expenses will have to be met, and the Company made an additional capital contribution of USD 1.5 million to cover the final stage of the project until COD. MPCES expects that nearly the entire amount of this additional funding will be recovered through proceeds from the agreed sale of the plant from contractually agreed closing adjustments to the purchase price.
[END OF RELEASE]

About MPC Energy Solutions
MPC Energy Solutions develops, builds, owns and operates renewable energy projects, with its current focus on utility-scale solar photovoltaics (PV) in Central America. More details at http://www.mpc-energysolutions.com (http://www.mpc-energysolutions.com/)
Media contacts
MPC Energy Solutions NV
Investor Relations & Public Relations
Email: ir@mpc-energysolutions.com
This information is subject to the disclosure requirements pursuant to section 5-12 of the Norwegian Securities Trading Act and the Market Abuse Regulation (MAR).
Attachments
MPC Energy Solutions’ solar plant in Guatemala enters testing and commissioning phase
Select market data provided by ICE Data Services. Select reference data provided by FactSet. Copyright © 2026 FactSet Research Systems Inc.Copyright © 2026, American Bankers Association. CUSIP Database provided by FactSet Research Systems Inc. All rights reserved. SEC fillings and other documents provided by Quartr.© 2026 TradingView, Inc.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply