India curtailed 8,133 GWh solar power in Q1 to ‘maintain grid security’: Centre informs Parliament – The Hindu

You are logged in
Loading…
You don’t have any Active Subscription.
Subscribed with another email? Logout and Login with that one.
Your active subscription(s)
Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription
Products you’ve access to
Additional Subscription Benefits
Account Settings
Need help with your subscription?
July 28, 2026e-Paper
The View From India Looking at World Affairs from the Indian perspective.
First Day First Show News and reviews from the world of cinema and streaming.
Today's Cache Your download of the top 5 technology stories of the day.
Science For All The weekly newsletter from science writers takes the jargon out of science and puts the fun in!
Data Point Decoding the headlines with facts, figures, and numbers
THEdge At the cutting edge of education and careers
Health Matters Ramya Kannan writes to you on getting to good health, and staying there
Gender Agenda Stories from beyond the binary.
The Hindu On Books Books of the week, reviews, excerpts, new titles and features.
July 28, 2026e-Paper
Published – July 28, 2026 08:26 pm IST – New Delhi
Rooftop solar power plants get traction | Photo Credit: The Hindu
India curtailed 8,133 gigawatt-hour (GWh) of solar power during the April–June quarter this year, according to Minister of State for New and Renewable Energy Shripad Yesso Naik.
The curtailment and restriction were instituted to “maintain grid security” and “due to mismatch between commissioning of transmission lines and renewable energy projects, he informed parliament, quoting figures from the Grid Controller of India.
Curtailment is when power-grid operators limit the power output from generating sources to maintain grid stability. A total of 2,417 GWh of solar energy curtailment was carried out in April this year, 3,235 GWh in May and 2,481 GWh in June.
As on June 30, India has installed solar capacity of up to 162.15 GW, which is inclusive of 125.6 GW of utility scale projects, 30.11 GW of rooftop projects and 6.43 GW of off-grid projects.
Separately, Mr. Naik also told the upper house that since its implementation in February 2024, the PM Surya Ghar scheme has received more than 75 lakh applications, as on July 22.
More than 39.7 lakh rooftop solar (RTS) systems with a cumulative installed capacity of 14,180.90 MW have been installed, he added.
Mr. Naik also said the scheme has reached out to more than 48 lakh households having released ₹27,343.9 crore as Central Financial Assistance (CFA) until June 27.
Published – July 28, 2026 08:26 pm IST
solar / power (infrastructure) / business (general) / renewable energy / green infrastrucutre
Copyright© 2026, THG PUBLISHING PVT LTD. or its affiliated companies. All rights reserved.
BACK TO TOPBack to Top
Terms & conditions  |  Institutional Subscriber
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply