Kannur Airport to Go Solar with 4 MWp Plant – Construction World

The project has been implemented by Kannur International Airport (KIAL) under the capital expenditure model. It comprises 2.163 MWp of ground-mounted solar capacity and 1.841 MWp of carport solar capacity, with the installations located at the airport’s carpark area.
KIAL had invited tenders for the project in February 2025. The original scope included 1.75 MWp of carport solar and 2.25 MWp of ground-mounted capacity, along with the design, supply, installation, testing, commissioning, operation and maintenance of the system.
Oriana Power received the order from KIAL for the project and undertook the engineering, procurement and construction work. Its scope also covered operation and maintenance, with the maintenance period set at five years after completion. The official Kerala e-tendering record describes the work as a 4 MWp grid-connected solar photovoltaic system.
The plant is intended to meet a substantial share of the airport’s daytime electricity demand. KIAL expects the project to generate several hundred thousand units of electricity each month and estimates that it could reduce power costs by about Rs. 3 mn per month. The project adds to a wider shift among Indian airports towards solar power, following similar initiatives at airports including Kochi, Hyderabad and Ahmedabad.
Kannur International Airport in Kerala has completed a 4 MWp grid-connected solar power project comprising ground-mounted and carport installations. The plant is scheduled to be formally inaugurated by Kerala Chief Minister V. D. Satheesan on September 28. The project has been implemented by Kannur International Airport (KIAL) under the capital expenditure model. It comprises 2.163 MWp of ground-mounted solar capacity and 1.841 MWp of carport solar capacity, with the installations located at the airport’s carpark area. KIAL had invited tenders for the project in February 2025. The original scope included 1.75 MWp of carport solar and 2.25 MWp of ground-mounted capacity, along with the design, supply, installation, testing, commissioning, operation and maintenance of the system. Oriana Power received the order from KIAL for the project and undertook the engineering, procurement and construction work. Its scope also covered operation and maintenance, with the maintenance period set at five years after completion. The official Kerala e-tendering record describes the work as a 4 MWp grid-connected solar photovoltaic system. The plant is intended to meet a substantial share of the airport’s daytime electricity demand. KIAL expects the project to generate several hundred thousand units of electricity each month and estimates that it could reduce power costs by about Rs. 3 mn per month. The project adds to a wider shift among Indian airports towards solar power, following similar initiatives at airports including Kochi, Hyderabad and Ahmedabad.
Passive design is an integral part of energy-efficient architecture. Sophisticated building systems also contribute to this end. But what role do materials play in enhancing a building’s energy-efficiency?“Material selection is one of the earliest opportunities to influence how a building performs,” says Tejbeer Singh, Principal Architect & Founder, Expressionist by Tejbeer Singh. “The objective is not simply to select materials that look appropriate but to understand how they behave within the climate and construction system.”To read the full article Click Here ..
India’s infrastructure sector is building at a scale few markets can match. New highways, expressways, metros, bridges and complex engineering projects are transforming the country’s landscape. Yet, behind this rapid expansion is a growing concern within the contracting community: Can infrastructure be delivered sustainably when competition pushes prices below commercially viable levels?For Praveen Sethia, Founder & Director, Infra Advisors, who moderated the discussion, the question goes beyond the contractor’s commercial interests. Contractors may be one of the two parties to a contract,..
Gurugram’s luxury housing market has expanded beyond its traditional prime locations, with corridors such as Dwarka Expressway and Golf Course Extension Road emerging as key centres for premium residential development. Larger homes, integrated developments and amenity-led communities are attracting demand from end-users and investors.A 2025 report by Sotheby’s International Realty in collaboration with CRE Matrix identified Gurugram as India’s fastest-growing ultra-luxury housing market. The city overtook Mumbai in total sales value for homes priced above Rs 10 crore, recording nearly Rs..
Get daily newsletters around different themes from Construction world.
Don’t miss out on valuable insights and opportunities
to connect with like minded professionals

A-303, Navbharat Estates, Zakaria Bunder Road, Sewri (West), Mumbai – 400 015, Maharashtra, India
By creating an account, you agree to our Terms and Conditions and have read and acknowledge the Privacy Policy

test
Don’t miss out on valuable insights and opportunities
to connect with like minded professionals

By creating an account, you agree to our
Terms and Conditions and have read and acknowledge the Privacy Policy

test

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply