The more-than $1 billion (USD 700 million) Waratah super battery built by Akaysha Energy on the site of the former Munmorah coal-fired power station on the New South Wales (NSW) Central Coast has reached full commercial operations.
With a total capacity of 850 MW and storage of 1,680 MWh, the Waratah battery energy storage system (BESS) is set to play a key role in NSW’s energy transformation, supporting the growing volume of renewable energy entering the grid and helping to deliver reliable electricity as ageing coal-fired power stations retire.
NSW Energy Minister Penny Sharpe confirmed on Monday that the battery has now received approval to operate at full capacity from the Australian Energy Market Operator (AEMO).
“The Waratah Super Battery is a game changer for NSW,” she said. “As ageing coal-fired power stations retire, this project will help keep the lights on for homes and businesses while enabling more renewable energy to flow through the grid.”
“This is exactly the kind of infrastructure NSW needs to deliver a reliable, affordable and modern energy system for generations to come.”
The BESS forms the foundation of the Waratah Super Battery Project, that also includes a 700 MW / 1,400 MWh system integrity protection scheme (SIPS) control system delivered by transmission company Transgrid. Together, the battery and control system are designed to act like a giant shock absorber for the grid, helping keep the system secure when major transmission lines are disrupted. At maximum output, the facility is capable of powering up to 340,000 NSW households at peak demand.
Transgrid Chief Executive Officer (CEO) Brett Redman said the SIPS control system is the “largest and most innovative” in Australia, capable of detecting network issues in real time and responding in real time, ensuring continuity of power supply for households and businesses.
“The delivery of the Waratah Super Battery provides an additional level of safeguard as coal plants retire and critical transmission infrastructure is built to connect more renewable energy into the Sydney, Illawarra and Hunter load centres,” he said.
The battery was due to commence full operations in late 2025 but a “catastrophic” failure of one of three giant transformers just days from final testing caused a major delay.
Akaysha CEO Nick Carter said the Waratah battery has been a “complex and demanding” project.
“This project tested us in many ways, but the team kept going, solved the problems in front of them, and delivered,” he said, adding it is a test testament to the grit, perseverance, and problem-solving capability of the Akaysha team.
“We are proud, grateful and humbled to reach this point, and focused now on the important role Waratah will play in supporting a more reliable, secure and renewable NSW electricity system,” he said.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: [email protected].
Comments
Please login to comment
The new issue of pv magazine Global is out now!
Available in print and digital – get your copy today!
You have no items in your basket.