Bob Watts, executive director of Chester County Solid Waste Authority, points out features of a well to capture landfill gas at Lanchester Landfill on Monday, June 1, 2026.
Bob Watts, executive director of Chester County Solid Waste Authority, points out features of a well to capture landfill gas at Lanchester Landfill on Monday, June 1, 2026.
 
An out-of-court settlement has cleared the way for a new 3-megawatt, 20-acre solar panel array to be built at Lanchester Landfill and Reclamation Center in Caernarvon Township.
The energy produced by the solar panels will power a facility on site that converts landfill emissions into commercial-grade natural gas, according to officials.
The planned solar array is the second such project from the Chester County Solid Waste Authority, which has diversified its operations at the Lanchester landfill since taking over operation of the landfill in 1984.
The Lanchester landfill serves 49 Chester County municipalities and Caernarvon Township, though most of the landfill is located within the borders of Lancaster County. About 150 garbage trucks arrive every day to dump waste into the active portion of the landfill, according to Bob Watts, executive director of the authority.
The solar-powered natural gas conversion facility will join a water treatment plant on site, a hiking trail network and a disc golf course on portions of the landfill that are already capped and covered.
The Caernarvon Township zoning hearing board initially rejected the project’s zoning application in April, raising concerns about the array’s ability to withstand high winds and plans of the developer, Hershey-based Coral Reef Partners, to keep transmission lines above ground.
It takes reporters, editors, and resources to do this work right. Your donation keeps that work alive.
Those concerns were easily resolved after Coral Reef appealed the denial, according to attorneys for both parties. The waste authority and representatives of the contractor gave members of the zoning board a tour of the landfill and a deeper explanation of project designs that satisfied their concerns, zoning board solicitor Neil Albert said.
The two sides reached a settlement Aug. 21, clearing a major hurdle to start construction.
Coral Reef Partners is still awaiting permit approvals from the Pennsylvania Department of Environmental Protection, Watts said.
The new gas processing facility the solar arrays will eventually power is slated to become operational in the spring, Watts said. The facility, to be built and operated by French firm Waga Energy, will purify captured landfill gases and sell them as commercial natural gas, increasing the landfill’s value as an energy source. The product is known in the energy industry as “renewable natural gas.”
The new system could net the authority about $500,000 in annual revenue, about twice what it has received in recent years from selling a lower grade of natural gas the authority currently draws from the landfill, Watts said.
Success! An email has been sent to with a link to confirm list signup.
Error! There was an error processing your request.
A French company is moving on a multi-million-dollar plan that would convert gas from a Lanc…
Nicole Bell said she thinks her 16-year-old son, Jonaston Martin, was killed Saturday night …
Amish women had been quietly making quilts for more than a century in Lancaster County. Everything changed in the 1970s when collectors arrived in town.
Conestoga Valley, Donegal and Elizabethtown Area high schools are in the running for a $1 mi…
Your browser is out of date and potentially vulnerable to security risks.
We recommend switching to one of the following browsers:

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply