PSC hearing questions fire protection for Cass County battery site – North Dakota Monitor

Public Service Commissioner Jill Kringstad points at a map of a planned battery storage site in Cass County during an Oct. 23, 2026, hearing in Casselton, North Dakota. (Photo by Jeff Beach/North Dakota Monitor)
CASSELTON, N.D. — The chair of the North Dakota Public Service Commission on Friday expressed concerns that a large battery storage project in Cass County would have to rely on Casselton for fire protection without Casselton having any say in the project’s approval. 
The project is called Harmony Storage and would sit next to a solar farm that is under construction in Harmony Township, east of Casselton. Both projects are led by Minnesota-based Geronimo Power.
One concern with large battery storage is the risk of fire from overheating batteries. 
Geronimo representatives sought to reassure the three-person commission that the risk of fire is low and the battery storage system is designed to prevent a fire from spreading. 
If a fire department needs to respond to Harmony Township, it would come from Casselton, which Commission Chair Randy Christmann noted has no say in the project. 
2nd Fargo-area data center would use double the power of Harwood site

“This still does concern me that we have a township approving a project, and then the project developer telling the fire department how they’re going to have to handle this project if this worst case happens,” Christmann said. 
Casselton Fire Chief John Hejl said in an interview after the meeting that dealing with a fire at a battery storage site would be similar to how it would deal with a battery-powered vehicle catching fire. He said containing the fire would be key. 
He said the fire department, which provides fire protection for 12 townships, has met with Geronimo on fire response to the solar farm and expects to meet again on the battery storage. 
“We’ll just continue talks with Geronimo if and when or however the project moves and kind of just take it from there,” said Hejl, who attended a portion of the hearing. 
The commission heard testimony from Geronimo representatives and from members of the public. A decision to approve or deny Geronimo’s application will come later. 
The 200-megawatt solar farm had previously been approved by PSC. The solar farm and battery storage and a proposed data center would be a part of what Geronimo calls Harmony Energy Park near the Bison Substation east of Casselton and north of Mapleton. 
Friday’s hearing was limited to the $249 million storage site, which could hold 200 megawatts of power for up to four hours. 
The storage site would be more than three-fourths of a mile away from the nearest residence, complying with both state and local setback rules, Geronimo officials said.
They also addressed noise, which would mostly come from fans to keep the batteries cool. 
Geronimo officials said their models show the site would comply with the township’s noise limit of 45 decibels at 1 mile from the site.
The company will also submit a study of the noise that might come from electronic components after the facility is farther along in the design process. 
Perry Rust, a Harmony Township landowner, said the commission should consider the impact of all of the energy development projects in the area around Harmony Township. 
While the battery storage site will only take up about 12 acres, when coupled with other projects, such as the data center and more power generation, there could be profound change for the rural lifestyle of Cass County, he said. 
“I urge the commission to evaluate the cumulative infrastructure domino effect that’s happening across our townships, rather than just viewing this application in isolation,” Rust said.
Reach North Dakota Monitor deputy editor Jeff Beach at [email protected]
GET THE MORNING HEADLINES.
by Jeff Beach, North Dakota Monitor
October 23, 2026
by Jeff Beach, North Dakota Monitor
October 23, 2026
CASSELTON, N.D. — The chair of the North Dakota Public Service Commission on Friday expressed concerns that a large battery storage project in Cass County would have to rely on Casselton for fire protection without Casselton having any say in the project’s approval. 
The project is called Harmony Storage and would sit next to a solar farm that is under construction in Harmony Township, east of Casselton. Both projects are led by Minnesota-based Geronimo Power.
One concern with large battery storage is the risk of fire from overheating batteries. 
Geronimo representatives sought to reassure the three-person commission that the risk of fire is low and the battery storage system is designed to prevent a fire from spreading. 
If a fire department needs to respond to Harmony Township, it would come from Casselton, which Commission Chair Randy Christmann noted has no say in the project. 
2nd Fargo-area data center would use double the power of Harwood site

“This still does concern me that we have a township approving a project, and then the project developer telling the fire department how they’re going to have to handle this project if this worst case happens,” Christmann said. 
Casselton Fire Chief John Hejl said in an interview after the meeting that dealing with a fire at a battery storage site would be similar to how it would deal with a battery-powered vehicle catching fire. He said containing the fire would be key. 
He said the fire department, which provides fire protection for 12 townships, has met with Geronimo on fire response to the solar farm and expects to meet again on the battery storage. 
“We’ll just continue talks with Geronimo if and when or however the project moves and kind of just take it from there,” said Hejl, who attended a portion of the hearing. 
The commission heard testimony from Geronimo representatives and from members of the public. A decision to approve or deny Geronimo’s application will come later. 
The 200-megawatt solar farm had previously been approved by PSC. The solar farm and battery storage and a proposed data center would be a part of what Geronimo calls Harmony Energy Park near the Bison Substation east of Casselton and north of Mapleton. 
Friday’s hearing was limited to the $249 million storage site, which could hold 200 megawatts of power for up to four hours. 
The storage site would be more than three-fourths of a mile away from the nearest residence, complying with both state and local setback rules, Geronimo officials said.
They also addressed noise, which would mostly come from fans to keep the batteries cool. 
Geronimo officials said their models show the site would comply with the township’s noise limit of 45 decibels at 1 mile from the site.
The company will also submit a study of the noise that might come from electronic components after the facility is farther along in the design process. 
Perry Rust, a Harmony Township landowner, said the commission should consider the impact of all of the energy development projects in the area around Harmony Township. 
While the battery storage site will only take up about 12 acres, when coupled with other projects, such as the data center and more power generation, there could be profound change for the rural lifestyle of Cass County, he said. 
“I urge the commission to evaluate the cumulative infrastructure domino effect that’s happening across our townships, rather than just viewing this application in isolation,” Rust said.
Reach North Dakota Monitor deputy editor Jeff Beach at jbeach@northdakotamonitor.com
North Dakota Monitor is part of States Newsroom, a nonprofit news network supported by grants and a coalition of donors as a 501c(3) public charity. North Dakota Monitor maintains editorial independence. Contact Editor Amy Dalrymple for questions: info@northdakotamonitor.com.
Our stories may be republished online or in print under Creative Commons license CC BY-NC-ND 4.0. We ask that you edit only for style or to shorten, provide proper attribution and link to our website. AP and Getty images may not be republished. Please see our republishing guidelines for use of any other photos and graphics.
Deputy editor Jeff Beach is based in the Fargo area. Interest areas include agriculture, renewable energy and rural issues. You can reach him at [email protected].
North Dakota Monitor is part of States Newsroom, the nation’s largest state-focused nonprofit news organization.
© North Dakota Monitor, 2026
v1.143.0
North Dakota Monitor is a nonprofit, nonpartisan source for trusted news, commentary and insight into statewide policy and critical issues affecting the Peace Garden State.
We’re part of States Newsroom, the nation’s largest state-focused nonprofit news organization.
DEIJ Policy | Privacy Policy | Ethics Policy | AI Policy
Our stories may be republished online or in print under Creative Commons license CC BY-NC-ND 4.0. We ask that you edit only for style or to shorten, provide proper attribution and link to our website. (See full republishing guidelines.)
DEIJ Policy | Privacy Policy |
Ethics Policy | AI Policy
© North Dakota Monitor, 2026

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply