Elon Musk’s Photovoltaic Order: No Chinese Company Selected? German Firm Secures SpaceX’s First HJT Production Line Order 20 Days After Major Chinese Shareholder Exits Stake – 36Kr

The cost-effectiveness logic of Chinese photovoltaic equipment going global has failed under rules such as FEOC.
Energy Foresight learned that on November 10, German equipment manufacturer SINGULUS announced that it has signed the first heterojunction production line supply contract with SpaceX, with an amount exceeding 60 million euros.
Chinese equipment manufacturers were not included in this order, and the problem is not the quotation. Tesla’s factory construction application documents in Texas show that the $10.1 billion investment is highly dependent on subsidies to be economically viable; 45X grants subsidies based on output, with a total of $0.11 per watt for batteries and modules. Calculated based on the 100GW target, the annual credit is about $11 billion.
The FEOC clause (Foreign Entity of Concern rule) ties the credit eligibility to the identity of suppliers, and Chinese equity, debt or technology licensing of suppliers may invalidate the credit. Three weeks ago, SINGULUS just cleared all Chinese debts, equities and supervisors, and the payer is SpaceX.
What this order buys is a supplier entity that can pass the compliance review. The logic of Chinese equipment going global by relying on cost-effectiveness has failed entirely for the first time.
The buyer did not never have the idea of purchasing Chinese equipment. On March 20, 2026, Reuters reported that Tesla was negotiating a Chinese equipment procurement of about 2.9 billion US dollars, with Maxwell, Jiejia Weichuang and Laplace listed as candidates. After the news of the inspection of “two groups of people, one industrial chain” spread in early February, GCL, TCL Zhonghuan and Gaice successively confirmed that they had contacts, but in nine months, clarification announcements came one after another, and the order announcement never appeared.
The crux is not the progress of negotiations. 8.6 billion US dollars of Tesla’s factory is for equipment, which is a one-time capital expenditure; The 45X credit is issued annually based on output and runs through the whole life cycle of the project. No matter how cheap Chinese equipment is, what it saves is only a small part of the former.
The Ministry of Finance and the IRS confirmed in Notice 2026-15 that intellectual property licensing can constitute “effective control” under specific conditions; equity and debt relationships are separately identified according to the thresholds in the FEOC/PFE rules. Once a supplier is linked to a prohibited foreign entity, the manufacturer’s 45X credit has to be re-reviewed; the specific definition of prohibited entities still leaves room for clarification.
One is the one-time equipment price difference, and the other is the cash flow issued annually that determines whether the project can be established. The two are not in the same order of magnitude, and the procurement department has no reason to exchange the latter for the former.
Therefore, Chinese equipment manufacturers are excluded, which has nothing to do with product performance. Its appearance on the supplier list will prevent the buyer from getting the money that makes the project viable. What the buyer avoids is its own compliance risk, and the technical selection has not happened at all. Those “contacts”, “inspections” and “candidates” in the past nine months have never been the prelude to the order — This transaction structure cannot pass the review from the very beginning. The market misread the clarification announcements one by one as “the negotiation has not been completed”.
Since identity determines eligibility, the winner must be an entity that is clean under the regulatory caliber. SINGULUS achieved revenue of 60.4 million euros in the first nine months of 2026, with EBIT (earnings before interest and tax) of 1.2 million euros, 312 employees, and 47.1 million euros of orders on hand as of September 30 — a 60 million euro production line exceeds all its orders on hand. Such a scale has no advantages in production capacity or delivery.
The series of actions it completed three weeks ago correspond item by item to the identification clues of FEOC.
On October 21, 2026, SINGULUS borrowed 22.75 million euros of subordinated secured loans, all of which were used to pay off the debts to Triumph Technology Group (Triumph under China National Building Material) and its related parties, and the related 15.3 million euros of orders were written off; Triumph transferred 16.75% of its shares to German investors, and the dispatched supervisor resigned on the same day.
The announcement on November 10 made it clear that the “technical partner” who paid twice in March and October is SpaceX. Debt, equity and control are exactly the three calibers repeatedly cited in the identification of “Foreign Entity of Concern”. The announcement on October 21 also specially thanked China National Building Material for its many years of cooperation, saying that the two sides have jointly made progress in thin-film solar technology and realized industrialization.
SpaceX spent twice in this transaction: One is to transform the seller into a qualified entity, and the other is to place an order with this entity. The first sum determines whether the second sum can be spent.
Twenty days, from clearing accounts to signing the contract, there is no room for price comparison in the middle. The premise of the first order transaction is to first have a legal entity that can pass the review, and equipment procurement comes after this matter. What is cleared is the legal relationship, and the technical relationship remains in the announcement.
The rule examines the legal relationship that can be filled in the form, and the technical source is not in the form. SINGULUS SOLAR GmbH under the group was established in June 2024 as a joint venture with Jinchen Co., Ltd., with Jinchen holding 49% of the shares, which is exactly engaged in TOPCon and HJT turnkey full lines (the equipment manufacturer completes installation and commissioning, and the customer can start operation after taking over). This shareholding ratio was listed in the list of participating and holding subsidiaries in the 2026 semi-annual report.
The Chinese majority shareholder left, but the Chinese joint venture partner still remains. This practice in the industry has become routine: In order to avoid the 25% shareholding identification line, Chinese-funded enterprises such as Canadian Solar, JA Solar and LONGi have reduced their Chinese-funded shareholding to 24.9% in some overseas projects. Compliance has become a structure that can be designed. Chinese manufacturers going global compete on transaction arrangements instead of equipment quotations.
The trouble is that the most realistic road is watched at both ends. Joint venture plus technology licensing is one of the few arrangements that can protect both the market and technology at present; FEOC lists Chinese technology licenses that constitute effective control as risks, while China’s Announcement No. 48 lists HJT P-type technologies and equipment with AM0 efficiency ≥ 20.5% as restricted exports. The registration before export takes effect immediately, and perovskite tandem is planned to be prohibited from export. AM0 is the illumination standard outside the atmosphere, which points exactly to the space scenario. One list checks your identity to enter, and the other checks what you can take out, clamping the transaction structure itself.
In the market on November 11, this change was not priced. Maxwell shares fell sharply, Jiejia Weichuang and Laplace moved lower synchronously; on the other side, Yamatong had three consecutive daily limits, Zerun New Energy rose 20.01%, Jinchen Co., Ltd. rose 9.98%, and ten stocks hit the daily limit. The ones that fell are the leading equipment manufacturers that have included the overseas order expectation into their valuations, and the ones that rose are the concept stocks without overseas orders.
Among them, Jinchen Co., Ltd. is a 49% shareholder of SINGULUS’s joint venture, which should have been the most direct beneficiary target of the “eligibility logic”, but the market attribution on that day fell on the “Musk concept”. The market is still pricing this news according to the old framework: equipment stocks depend on orders, and concept stocks depend on headlines. The rise and fall on that day measured the order expectation and concept popularity, but did not measure the rule itself. The rule has changed, but the pricing method has not.
SINGULUS officially wrote that after the cooperation is gradually expanded, it will “support more than 100GW of production equipment”, and what is implemented is a production line to be delivered in the first half of 2027; Tesla’s $10.1 billion factory will not be put into commercial operation until the first quarter of 2029. A heterojunction industry insider quoted by Shanghai Securities News said that the feasibility of Chinese photovoltaic enterprises participating in the construction of this factory is “relatively low”.
The 14 US tariff exemptions for photovoltaic equipment are only extended to January 9, 2027, and the consultation period for China’s “Catalogue” draft ends on November 15. The most noteworthy date among these dates is November 15: which efficiency gear the official draft sets for HJT restrictions determines whether Chinese manufacturers can still incorporate the technology into a compliant structure. Before that, no matter how many rumors of “Musk’s team coming for inspection” there are, they cannot be exchanged for an order announcement.
该文观点仅代表作者本人,36氪平台仅提供信息存储空间服务。
36kr Europe (eu.36kr.com) delivers global business and markets news, data, analysis, and video to the world, dedicated to building value and providing business service for companies’ global expansion.
© 2024 36kr.com. All rights reserved.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply