Fate of controversial £1bn Norfolk countryside solar farm to be discussed next week – Norwich Evening News

Share
Share
The fate of a £1 billion solar farm earmarked for the Norfolk countryside could become clearer when hearings resume next week.
The second round of hearings examining the East Pye solar farm will take place at Mercure Norwich Hotel in Boundary Road.
It will help to determine whether the 2,700-acre solar farm should be built on land across south Norfolk, and follows the first round of discussions in September.
The hearings will take place at the Mercure Norwich Hotel (Image: Google Maps)
The arrays of panels will stretch from Tivetshall and Great Moulton in the west to Seething in the east, impacting villages including Hempnall, Saxlingham, Shotesham and Woodton.
The first session at 4pm on Tuesday will be a preliminary hearing, where people registered to speak can make their views on the project heard.
So far, 22 people have asked to speak.
A map of where the East Pye solar farm (Image: East Pye)
Wednesday’s hearing will consider compulsory acquisition and the temporary possession of land.
The hearing will assess whether compulsory acquisition is in the public interest.
The applicant, East Pye, will be asked to present its case for compulsory acquisition.
Site inspections will also take place next week, with Tibenham Airfield among the locations to be visited.
Aviation experts say the scheme, a mile from the airfield, poses serious safety risks and could endanger lives.
Officials will take the unusual step of visiting homes during the inspections.
More hearings are planned for December, before the examination ends in February next year.
After that, David Cliff, the planning inspectorate, will have three months to make a recommendation to Miatta Fahnbulleh, the energy secretary.
Due to its size, the project is classed as nationally significant, meaning the government has the final say on the scheme.
Almost 2,000 members of the public have made representations about the plans, many of them opposing the development.
Developer Island Green Power says the scheme could generate up to 500 megawatts of electricity, enough to power about 115,000 homes a year.
Share
This website and associated newspapers adhere to the Independent Press Standards Organisation’s Editors’ Code of Practice. If you have a complaint about the editorial content which relates to inaccuracy or intrusion, then please contact the editor here. If you are dissatisfied with the response provided you can contact IPSO here
© 2001-2026. The Norwich Evening News is owned and operated by Newsquest Media Group Ltd, an audited local newspaper network.
Visit newsquest.co.uk to view our policies, terms and legal agreements.
The Echo Building, 18 Albert Road, Bournemouth, England BH1 1BZ. Registered in England & Wales | 01676637
Data returned from the Piano ‘meterActive/meterExpired’ callback event.
As a subscriber, you are shown 80% less display advertising when reading our articles.
Those ads you do see are predominantly from local businesses promoting local services.
These adverts enable local businesses to get in front of their target audience – the local community.
It is important that we continue to promote these adverts as our local businesses need as much support as possible during these challenging times.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply