CUMBRAE Community Council is set to object to plans to give developers a further three years to begin work on a controversial solar farm and battery storage development near Millport.
Comsol Energy Limited has lodged an application with North Ayrshire Council seeking more time to implement its existing permission for a photovoltaic solar farm, battery energy storage systems and associated infrastructure on land north-east of Wee Minnemoer.
The community council says it will oppose the extension, pointing to the strength of local objections when the latest proposals were considered in 2023.
It said in a message to residents on its Facebook page: “Cumbrae Community Council will object. In 2023, 95 per cent of the comments sent to the council were against this plan.
“We are not against green energy.
More:Millport solar farm protest is ‘brolly good’ effort
“More than half of you told us you would support an energy project owned by the island, as long as it is in a better place.”
The group described the development as a “large-scale solar farm and giant batteries” proposed at Minnemoer, near the Glaid Stone at one of the highest points on Cumbrae.
The history of proposals for the site stretches back more than a decade, with the community council stating that the first plans were submitted in 2015.
An earlier approved scheme was not developed before its permission expired, while the latest application was rejected by North Ayrshire Council’s Planning Committee in June 2023.
The community council pointed out that all councillors on the committee voted against the proposal.
However, Comsol appealed the decision and planning permission was subsequently granted by a Scottish Government reporter on February 9, 2024.
With the existing permission approaching its implementation deadline, Comsol has now applied under Section 42 of the Town and Country Planning (Scotland) Act 1997 for a further three-year period in which to start the development.
The company says there would be no changes to the approved development, its layout, capacity or access, with the application solely seeking additional time to commence work.
In its supporting statement, Comsol says delays have resulted from major reforms to the UK’s electricity grid connection process.
The National Energy System Operator launched a reassessment of existing projects in 2025, requiring developers to revisit their connection timescales and enter into new discussions.
Solar farm plan objections in 2023 included a colourful cavalcade of protesters who raised their brollies to object. (Image: NQ)
Comsol says this created “significant uncertainty” over when the Cumbrae project could secure a connection to the grid.
However, it received a revised connection offer in September 2026 and formally accepted it the following month, with a confirmed grid connection date of September 2029.
The developers argue this gives the project the certainty required to move forward but means more time is needed to implement the planning permission.
Solar farm plan objections in 2023 included a colourful cavalcade of protesters who raised their brollies to object. (Image: Submitted)
Its supporting statement describes the proposed extension as a “logical and pragmatic amendment” which would not raise any new material planning matters and would help deliver an already-approved renewable energy project.
But the community council is now urging islanders to make their views known before North Ayrshire Council determines the application.
It said: “You have a voice.”
Residents can view the application and submit representations through North Ayrshire Council’s planning portal, with the community council highlighting Thursday, November 26 as the deadline for comments.
Share
This website and associated newspapers adhere to the Independent Press Standards Organisation’s Editors’ Code of Practice. If you have a complaint about the editorial content which relates to inaccuracy or intrusion, then please contact the editor here. If you are dissatisfied with the response provided you can contact IPSO here
© 2001-2026. The Largs and Millport Weekly News is owned and operated by Newsquest Media Group Ltd, an audited local newspaper network.
Visit newsquest.co.uk to view our policies, terms and legal agreements.
The Echo Building, 18 Albert Road, Bournemouth, England BH1 1BZ. Registered in England & Wales | 01676637
Data returned from the Piano ‘meterActive/meterExpired’ callback event.
As a subscriber, you are shown 80% less display advertising when reading our articles.
Those ads you do see are predominantly from local businesses promoting local services.
These adverts enable local businesses to get in front of their target audience – the local community.
It is important that we continue to promote these adverts as our local businesses need as much support as possible during these challenging times.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply