Work is ongoing with mounting structures for the solar panels being installed.
Story by Roy Nollkamper
It’s no great surprise that Glacier and Toole counties have become the center of a large wind generation project, which has been completed over the last dozen years. We all know that the wind has quite a reputation along the Rocky Mountain Front. The 266 wind turbines, which produce 399 megawatts of power, have been a familiar sight on the horizon.
But what may not be familiar to most of the residents of Glacier and Toole counties, is the huge solar generation facility that is under construction southeast of Cut Bank.
A trip down the Sullivan’s Bridge Road will reveal the location of the largest solar generation project in the state of Montana. It’s also the location of three large substations to handle the power generated by the wind farms and the output of the Glacier Solar Park.
From the substations, owned by Northwest Energy, Montana Alberta Tie Line and BHE Energy Montana, the power is carried through the Montana Alberta Tie Line (MATL), owned by BHE US Transmission which is an affiliate of BSE Montana, and fed into the electrical grid serving Montana and eventually into the national electrical grid.
Planning for the solar park has been progressing for several years and over 1,500 acres of land has been purchased or leased. Construction started in October of 2025 with a crew of over 200 men. At this location over 200,000, yes, that’s not a typo, 200,000 solar panels are being installed. The project is expected to be on line by Spring of 2027. Total generation capacity of the project is 130 megawatts (mw) which is approximately one-fourth of the output of Hungry Horse Dam.
The influx of workers at the project has been very welcome to the area and short-term rentals and Airbnb units in Cut Bank, Shelby and even Conrad have been booked until the construction is completed. Other retail businesses have also experienced a welcome increase in sales for the past year. Many of the workforce travel with their families which has also led to an increase in student enrollment at the schools.
The Glacier Solar Park is managed by Berkshire Hathaway Energy Montana (BHE) based in Great Falls. BHE also manages the three wind generation sites near Cut Bank and the battery storage facility located in the BHE substation at the Glacier Solar Park. Total generation capacity of the entire complex is over 500 mw plus 75 mw storage at the battery site. The battery installation alone is large enough to power 60,000 residential homes for two hours.