India Solar Capacity Growth Faces Grid and Award Risks After FY28 – Urban Acres

India’s solar capacity growth is showing strong near-term momentum, but transmission bottlenecks, delayed power agreements and a slowdown in new renewable-energy awards could weaken expansion beyond FY28, according to a YES Securities report cited by Economic Times.
Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25, the report said. Installations remained strong in the first half of FY27, with 21 GW of solar AC capacity added during the period.
Rooftop and agricultural programmes are supporting this demand. The PM Surya Ghar scheme added 2.4 million rooftop systems in the first half of FY27, compared with 1.7 million systems during the whole of FY26, according to the report. The KUSUM programme is also supporting demand for domestically manufactured solar modules.
The stronger installation figures, however, are not being matched by the same pace of new project awards. Renewable-energy awards fell to 14.7 GW in FY26 from 40.6 GW in FY25. By August 10, 2026, only 4.7 GW had been awarded in FY27, the report said.
A further concern is that around 40–45 GW of awarded renewable-energy capacity had yet to secure power purchase or sale agreements. Without these agreements, projects may face uncertainty over offtake and execution, even after receiving an award.
Transmission constraints are adding another layer of risk. Solar curtailment reached 8,133 GWh between April and June 2026, with the report identifying Rajasthan and Gujarat as areas where limits on transmission and renewable-power evacuation are affecting grid performance. Curtailment occurs when available electricity cannot be transmitted or absorbed by the grid, reducing the amount of generated power that can be delivered.
The report said a construction pipeline of more than 150 GW should support demand for solar modules through FY28. That pipeline provides near-term visibility for manufacturers and project suppliers, but weaker fresh award activity could reduce volumes in FY29 and FY30.
This makes the conversion of awarded projects into signed power agreements and completed installations a central factor in the sector’s outlook. Transmission readiness will also determine whether new generation capacity can be integrated effectively, particularly in states that are emerging as major renewable-power centres.
Storage-linked tenders are becoming another source of demand, although the report noted that such projects could shift a larger share of investment towards battery storage. The balance between new generation, grid expansion and storage will therefore influence how quickly India can translate its solar project pipeline into operating capacity.
The near-term picture remains positive, supported by rooftop adoption, agricultural programmes and projects already under construction. The main risks identified by the report lie further ahead: slower project awards, unresolved power agreements and inadequate transmission capacity could weigh on solar-sector growth after FY28.

Welcome to Urban Acres, a leading think tank dedicated to promoting sustainable urban built environments in the face of climate change and the need for zero net carbon solutions.
© 2022 Urban Acres | All Rights Reserved

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply