Motion for rehearing filed in case that could determine future of 3,900-acre solar farm in Hinds Co. – WLBT

JACKSON, Miss. (WLBT) – A decision allowing a 3,900-acre solar farm to be built in western Hinds County could hinge on whether the documents related to that project were properly included in the Board of Supervisors’ minutes.
On Tuesday, Allison Lauderdale filed a motion for a rehearing in her case, challenging the county’s decision to grant two conditional use permits to Soul City Storage LLC and Soul City Energy LLC to allow for the construction of a solar farm near Bolton.
The motion comes two weeks after the Mississippi Court of Appeals upheld the board’s decision in a split opinion, essentially clearing the way for the controversial project.
Lauderdale, however, argues that the majority opinion, “overlooked or misapprehended” several points of law included in her argument.
The Hinds County resident initially argued that the Board of Supervisors “committed reversible error” when it failed to provide written findings related to its vote on the permits in its minutes – something required under the Hinds County Zoning ordinance.
The Court of Appeals disagreed, saying that by “incorporating the application, site plan, and all materials included with the original and supplemental conditional use permit applications” in the minutes, the board did just that.
Lauderdale, however, argues that the board didn’t include that information, saying that the court relied on a “boilerplate minute notation” showing the documents were included in the minutes, but that the documents themselves were never attached.
“The minutes do not include any motion adopting Soul City’s application as the board’s findings, nor do they include any motion certifying compliance with [zoning rules]. Reading such an action into the minutes from a clerical notation… is, at best, an act of inference, rather than the express showing required under the Zoning Ordinance,” she wrote.
Instead, she says the information that was included in court records were materials attached to the notice of appeal by Soul City, not anything the board itself attached to the minutes.
“Materials an applicant files with its appeal are part of the record before the board. They do not, by that fact, become the board’s written decision,” she said.
Lauderdale also said the court’s majority opinion also incorrectly concluded that the supervisors’ decision to approve the permits also included the several “self-imposed conditions” agreed to by Soul City officials, despite that the minutes from the board meeting in question “do not support that finding.”
“Neither resolution imposes, adopts, references, or conditions the permits on any commitment,” she wrote. “The only mention of any such commitment in the minutes is a summary of a Soul City representative’s remarks: ‘He emphasized no noise and no smell; trees will be planted for visual screen and road improvements on various roads in the area.’”
“A speaker’s remarks summarized in the minutes are discussion, not ‘formal action of the board,’” Lauderdale contended.
Officials with Apex Clean Energy, the Charlottesville, Virginia-based firm backing the project, gave WLBT a tour of the proposed solar farm site last year.
The company has agreed to 25-foot setbacks from existing road rights-of-way, so timber and vegetation along the roadways will be maintained. The farm also will include dozens of “wildlife corridors,” which will allow deer and other wildlife access to habitats, food, and water.
At a public hearing in August 2025, Audubon Mississippi Policy Director Jill Mastrototaro said the project would have “nominal impacts on any of those environmental considerations” brought up by opponents.
Want more WLBT news in your inbox? Click here to subscribe to our newsletter.
See a spelling or grammar error in our story? Please click here to report it and include the headline of the story in your email.
Copyright 2026 WLBT. All rights reserved.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply