Work starts on NZ’s largest approved solar farm between Taupō and Napier – NZ Herald

An artist's image of what the solar farm will look like when completed. Photo / Todd Corporation
Construction has begun on New Zealand’s largest approved solar farm, being built between Taupō and Napier.
Te Rahui solar farm is set to become a landmark alongside State Highway 5 and is a joint project between Nova Energy (owned by Todd Corporation) and Meridian Energy.
It is being built across
A “golden row” event was held on Wednesday to mark the installation of the first rows of panels.
The project will be completed in two stages and, when finished, will boast more than 700,000 solar panels, enough to power about 100,000 homes (producing about 400MW).
Work on stage one will continue into 2027, and the second stage could be completed by 2030.
However, the second stage is still subject to “commercial decisions” to get the official go-ahead.
The entire project will cost an estimated $660 million, making it a larger investment than Meridian Energy’s Harapaki wind farm, which cost about $450m and is located next to the same highway.
Nova Energy chief executive Rob Foster said the golden row event marked a milestone for the project.
“Every panel installed moves Te Rahui closer to delivering more renewable electricity for New Zealanders, while creating jobs and lasting benefits here in the region.”
Te Rahui is New Zealand’s largest solar farm to have gained consent to date, according to the organisations behind the project.
The project received consent in late 2022, and an appeal in the Environment Court was dismissed in 2024, paving the way for the project to proceed.
Solar panels typically have a lifespan of between 25 and 30 years.
The project’s consent includes a condition “that the components and infrastructure are disposed of in a way that maximises reuse and recycling”.
“For any parts that cannot be reused or recycled, [the consent holder is to ensure] that they are disposed of in an environmentally responsible way in accordance with industry best practice,” the consent reads.
Construction of a substation, a piece of infrastructure that connects the solar farm to the electrical grid, is also underway at the site.
The site was selected for its good exposure to sunlight, suitable landscape, proximity to existing grid infrastructure, and ability to accommodate a large-scale solar project.