MNRE rules out blanket ALMM deadline extension, sets up case-by-case exemption route – Power Peak Digest

The Ministry of New and Renewable Energy (MNRE) has decided not to grant a blanket extension to the June 1, 2026 deadline for mandatory sourcing of solar photovoltaic (PV) cells from the Approved List of Models and Manufacturers (ALMM) List-II. However, the ministry has introduced a case-by-case exemption mechanism for eligible net-metering and open-access renewable energy projects where investments have already been made.
The decision was issued through an office memorandum dated May 25, 2026, following consultations with stakeholders from the solar PV manufacturing and renewable energy development sectors.
According to the ministry, industry participants broadly supported policy continuity to maintain investor confidence in domestic solar manufacturing. At the same time, concerns were raised regarding projects that had already incurred substantial investments prior to the enforcement deadline.
The memorandum stated that genuine cases where solar modules had already reached project sites, installations had been completed but projects were yet to be commissioned, or developers had taken effective steps towards project implementation, would be considered for investment protection on a case-by-case basis.
The ministry has identified two categories under which eligible projects may apply for time extensions for compliance with ALMM List-II requirements.
Category I covers projects where 100% of the required solar PV modules were installed at the project site before June 1, 2026, but commissioning had not taken place by the deadline. Such projects are required to submit certification or approval from the Electrical Inspectorate confirming completion of direct current (DC) side installations, including module installation.
Category II applies to projects where developers had undertaken effective steps towards implementation but commissioning remained incomplete before the deadline. To qualify, developers are required to satisfy three conditions before June 1, 2026: possession of at least 75% of the required land through registered ownership, lease, or government allotment; achievement of financial closure; and receipt of in-principle connectivity approval with a specified start date.
Eligible renewable energy developers are required to submit applications through a dedicated online portal developed by the National Institute of Solar Energy (NISE) by June 30, 2026. Physical applications will not be accepted.
The MNRE said an expert committee will review applications on a project-wise basis, with field inspections to be carried out where necessary. Detailed operational procedures for examination of claims will be issued separately.
The memorandum also referred to a Ministry of Finance notification dated April 29, 2026, which classified the ongoing West Asia situation as war for the purpose of invoking force majeure provisions. Under the directive, contractual obligations affected by disruptions linked to the situation may receive extensions of two to four months without penalty, provided the affected parties were not already in default as of February 27, 2026.
Separately, the ministry clarified that residential net-metering consumers under the PM Surya Ghar: Muft Bijli Yojana (PMSG:MBY) who choose to opt for the “Give It Up” campaign and forgo central financial assistance will continue to remain governed by the scheme guidelines until March 31, 2027. Such consumers are required to apply through the scheme’s national portal.
The featured photograph is for representation only.
Four developers have won contracts to set up a total of 250 MW grid-connected wind power projects across India under Phase IX of Gujarat Urja Vikas Nigam Limited (GUVNL). The bidding was finalised on April 23, 2025. KPI Green Energy Limited secured 100 MW at a tariff of Rs 3.64 per kWh. Juniper Green Energy…
Read More Four firms win bids for 250 MW wind projects under GUVNL Phase-IX
The Government of Arunachal Pradesh has approved State Goods and Services Tax (SGST) reimbursement concessions for two major hydroelectric projects: the Subansiri Middle (Kamala) Hydro Electric Project and the 700 MW Tato-II Hydro Electric Project. Both projects are being implemented through joint ventures. The Subansiri Middle project is led by NHPC Limited, while the Tato-II…
Read More Arunachal Pradesh approves SGST reimbursement for hydro projects
Waaree Renewable Energy Technologies Limited has received a Letter of Award (LoA) worth Rs 3,463.3 million from Purvah Green Power Private Limited, a subsidiary of CESC Limited. The contract, awarded on June 2, 2025, is for engineering, procurement and construction (EPC) of 300 MW / 435 MWp Inter-State Transmission System (ISTS)-connected solar power projects in…
Read More Waaree secures contract for 300 MW solar project in Rajasthan
Larsen & Toubro (L&T) has incorporated a new wholly-owned subsidiary, Panipat Green Hydrogen Private Limited, to focus on green hydrogen initiatives.   Earlier, L&T had also set up L&T Green Energy Kandla Private Limited. This subsidiary is dedicated to developing green hydrogen and its derivatives, including green ammonia. These efforts are part of L&T’s plan to…
Read More L&T sets up green hydrogen subsidiary
Vikram Solar Limited has appointed Sameer Nagpal as Chief Executive Officer (CEO), effective March 20, 2026, as the company advances its capacity expansion plans. Nagpal brings over three decades of experience across multiple industries. He has held leadership roles at Livguard Energy Technologies, Dalmia Bharat Group, Shalimar Paints, Ingersoll Rand, Zicom, and Carrier Air Conditioning….
Read More Vikram Solar appoints Sameer Nagpal as CEO amid expansion push
Quaise Energy has partnered with Nevada Gold Mines (NGM) to explore deep geothermal energy for decarbonizing NGM’s TS power plant.  This collaboration aims to hybridize on-site power generation by utilizing geothermal heat from NGM’s land and subsurface resources, reducing reliance on fossil fuels and greenhouse gas emissions in the mining sector. This marks the first…
Read More Quaise Energy partners with Nevada Gold Mines to retrofit power plant with geothermal energy
Your email address will not be published. Required fields are marked *






Subscribe To Our Newsletter
Contact Us
info@powerpeakdigest.com
© 2026 Power Peak Digest. All rights reserved.

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply