The Midcontinent Independent System Operator is expected to have growing capacity surpluses over the next five years, according to the OMS-MISO survey.
The latest OMS-MISO survey marks a turnaround from two years ago, when the survey indicated that MISO faced possible shortfalls starting in 2025. The deficits were projected to grow over the following four years.
Now, it forecasts growing power supply margins, even with loads forecast to grow by 5.1% a year.
The survey indicates that MISO will have excess supplies above its planning reserve margin for the planning year that starts in June 2027 ranging from 4.6 MW to 12.7 MW, depending on the season.
Those surpluses could continue growing. Based on load forecasts from November, the survey indicates MISO’s excess capacity above forecast planning reserve margin requirements — which includes a buffer above expected peak loads — will grow from 11.5 GW in summer 2028 to 39 GW in the summer three years later. However, when considering load forecasts from April, those margins are significantly less, according to the presentation.
In the near term, solar and battery storage make up most of the capacity additions. By 2032, the roughly 100 GW of new supplies will be about 60% wind, solar and batteries and 40% gas-fired generation, according to the presentation.
MISO cautioned that there is uncertainty about the viability of the 87 GW of resources with signed generator interconnection agreements that haven’t been built. The grid operator said it is studying interconnection requests for another 192 GW.
So far this year, 3 GW of nameplate capacity has come online compared with 10.6 GW in all of last year, 7.6 GW in 2024 and 5.6 GW in 2023, according to MISO’s Generator Interconnection Queue Commercial Operation Dates Dashboard. Solar generation accounts for nearly 60% of the total 26.8 GW of capacity over that period.
MISO noted that it is switching to a “direct loss of load” resource accreditation methodology, which it said will value a resource’s contribution to reliability during the highest-risk periods. The change will come into effect for MISO’s 2028/29 planning year.
MISO runs the grid and wholesale power markets in 15 states and the Canadian province of Manitoba.
The OMS-MISO survey has become an increasingly important tool for states, utilities, MISO and stakeholders in understanding changing resource adequacy conditions across the grid operator’s footprint, Carrigan said.
The survey received a 99.5% participation rate, a record, he noted.
Get the free daily newsletter read by industry experts
The PJM Interconnection’s planned backstop auction is flawed, said CEO Brian Tierney. Separately, Pennsylvania Gov. Josh Shapiro said his administration will oppose rate hike requests that fail to meet affordability criteria.
The utility will supply a 1.4-GW Oracle data center under construction now, and it has submitted contracts to regulators for a 1-GW Google project also in the works.
Subscribe to Utility Dive for top news, trends & analysis
Sign up for the free newsletter.
Interested? Explore more of what has to offer.
Thanks for signing up! Please keep an eye out for a confirmation email from [email protected] To ensure we make it into your inbox regularly, add us to your allow list, mark us as a safe sender, or add us to your address book. Check out more from
Get the free daily newsletter read by industry experts
The PJM Interconnection’s planned backstop auction is flawed, said CEO Brian Tierney. Separately, Pennsylvania Gov. Josh Shapiro said his administration will oppose rate hike requests that fail to meet affordability criteria.
The utility will supply a 1.4-GW Oracle data center under construction now, and it has submitted contracts to regulators for a 1-GW Google project also in the works.
The free newsletter covering the top industry headlines