Ballynahinch Castle has lodged plans with Galway County Council for a major expansion of its solar installation that will supply around half of the five-star hotel’s annual electricity needs.
Yelsea Limited, the company that owns the luxury hotel, lodged an application last Friday to more than double the number of solar panels at its ground-mounted array on the estate to 928.
Did you know you can manage your profile, and explore all of the available newsletters from Connacht Tribune within your account.
The hotel currently generates around 24% of its annual power from an existing 172kWp solar installation that was installed in 2023. The proposed expansion would more than double its output, generating over 485,000kWh per year.
The application is accompanied by a Natura Impact Statement (NIS) and architectural impact assessment because the development is located within the curtilage of a protected structure and just 17 metres from a Special Area of Conservation (SAC).

The project would see the installation of 208 480W Aiko panels mounted on ground screws to accommodate uneven terrain, alongside 288 630W Horay panels supported on 16 galvanised steel frames on precast concrete ballast blocks.
Around 155 ballast blocks, each weighing approximately 750kg would be manufactured offsite using recycled building materials to eliminate the need for onsite concrete pouring.
The NIS notes that the site is located roughly 115 metres from Ballynahinch Lake and 200 metres from the Owenmore River, both of which hold high water quality status and support salmon and foraging otters.
While screening identified a potential construction-phase risk to water quality via surface runoff, the report concluded that the 12-week build would not adversely affect the integrity of the Connemara Bog Complex SAC.
However, strict mitigation measures would be required, including double-layered silt fencing, a ban on soil-moving works during rainfall warnings or forecasts exceeding 10mm over 24 hours, and oversight by a project ecologist.
The solar expansion forms part of a wider wave of development across the estate, with three other live planning applications currently before Galway County Council for a new 10-bedroom guest wing, an extension to office and staff facilities, and an upgraded wastewater treatment plant.
A decision on the solar array application is due on January 17, 2027.