South Africa’s own renewable energy developers have spent 15 years building the country’s independent power industry. Now they find themselves unable to lead a bid in Eskom’s most important renewable energy procurement to date.
On 2 October 2026, Eskom issued a request for qualification (RFQ E3612GXR) to select strategic partners for Eskom Green, its new renewable energy subsidiary. The aim is a five-year panel of partners to co-develop, finance and build up to 6 GW of solar PV, wind and battery storage, with Eskom contributing at least 2 GW of solar PV and 1 GW / 4 GWh of battery storage on its own land and sites. Responses close on 12 January 2027.
The opportunity is significant. But the qualifying rules are drawn so that virtually every indigenous South African developer and IPP fails before its submission is even considered. The grievance this has caused is real, and it sounds very much like what we heard a year ago about the Independent Transmission Projects (ITP) programme.
The eligibility rules
There is no explicit requirement for the size of a responding company. Size is imposed through four pass/fail mandatory criteria, and failing any one criterion means disqualification. As amended by four briefing notes, these are:
The detail is where local developers come unstuck. Only projects in commercial operation count – not those at financial close or under construction. Smaller projects, phases or clusters at the same site cannot be combined to reach 240 MW. The company must have been the developer, co-developer or sponsor, not a passive shareholder. Criteria 1 and 2 must be met by the Lead Member alone, or by a parent company that controls it.
Why the locals fail
The 240 MW requirement is the killer. In its own published clarification responses, Eskom records the point made by a respondent: only one operational solar PV or wind project of that size exists in South Africa.
This project is the 240 MW Mooi Plaats solar PV plant near Noupoort, which reached commercial operation in March 2026. It belongs to Envusa Energy, the joint venture of Anglo American and France’s EDF, with black-owned Pele Green Energy holding 20%. Even Envusa fails on its South African assets alone: its Koruson 2 cluster of Mooi Plaats and two 140 MW wind farms totals 520 MW, short of the 800 MW portfolio test.
The others fare worse:
The same applies to black-owned equity platforms such as African Rainbow Energy, H1 Holdings and Hulisani, and to other players whose projects were built to REIPPPP sizes.
A gap of the state’s own making
The irony is that local developers fail not for lack of capability, but because of the way the state procured renewable energy in the past.
For most of its history, REIPPPP capped individual projects – typically at 75 MW for solar PV and 140 MW for wind. Bid Window 5, awarded in 2021, still procured exactly those sizes. Local developers responded rationally. They built many projects of the size government asked for. South Africa’s renewable fleet is a portfolio of mid-sized plants, not giant single-site facilities.
The larger projects came only recently, through private wheeling and later bid windows. Many have now reached financial close or are under construction but have not yet reached commercial operation. Red Rocket’s Overberg, NOA’s Khauta South and Mulilo’s Beaufort West will all clear the 240 MW bar – but only some months after the closing date.
When asked directly whether Criterion 1 was intended to exclude South African IPPs from leading a response, Eskom said no. But it refused every remedy proposed, including recognising projects at financial close, combining phases at one site, or aligning the threshold with South African project sizes. It also declined to create a separate category for local developers. The exclusionary effect is the same, whatever the intent.
Who actually leads
The Eskom eligibility criteria work in favour of companies with large global portfolios. Experience anywhere in the world counts, and no South African experience is needed to pass Stage 1. The RFQ was later amended to accept offshore wind projects, which do not exist in South Africa, and the track record of fund managers and their other funds.
The likely leaders are therefore international players with operational renewable plants measured in gigawatts. Candidates include EDF, Copenhagen Infrastructure Partners (CIP), Scatec, Engie, ACWA Power, Masdar and TotalEnergies.
CIP shows how this works. The Danish fund manager and infrastructure developer has owned a majority of Mulilo since 2023. Mulilo will not qualify in its own right, but CIP may respond with Mulilo as part of its consortium. The rules allow a parent’s credentials to be used in only one bid, so CIP fronts the bid. Mulilo brings the South African pipeline.
SOLA, Red Rocket, NOA and Pele have no foreign parent to lean on. They must find a multinational willing to take them along.
Options for those left out
Local developers are not shut out entirely, but every route puts them in second place:
None of these gives a local company a seat at the table in its own name. The developers that built the industry become junior partners, while foreign firms hold the relationship with Eskom Green.
“SA Inc should have a primary seat at the table at this critical juncture to leverage our capabilities at every level – including local developers, local contractors and local manufacturers”, comments Manufacturing Circle Executive Director Philippa Rodseth.
We have seen this before
This is the second time in just over a year that the local industry has been bypassed. In July 2025, the Department of Electricity & Energy issued an RFQ for the first phase of the Independent Transmission Projects (ITP) programme, about 1064 km of new lines worth roughly R17-billion. Respondents had to prove experience of at least three independent transmission projects built in the past 15 years.
No South African company could meet that test, because Eskom, and later the National Transmission Company South Africa (NTCSA), had built all of the country’s transmission infrastructure. Local contractors, manufacturers and industry bodies warned that the criteria would sideline domestic industry.
They were proved right. On 15 December 2025, Minister Kgosientsho Ramokgopa named seven pre-qualified bidders from 17 respondents, all led by international companies, including China’s State Grid International Development Company (the international arm of the State Grid Corporation of China), Spain’s Grupo Cobra and Celeo Redes, and India’s Adani. Local firms were left to bid for EPC subcontracts.
The pattern is the same in both cases. A state monopoly, or a state programme, shapes the market for years. A qualifying test is then set at a level that the local industry it shaped cannot possibly meet. Local firms that would have led are recast as subcontractors and minority partners to foreign leads.
Local renewable energy developers and IPPs are now expressing the same grievance felt by the construction and engineering industry over the ITP. They believe the Eskom Green RFQ is designed, deliberately or not, to favour international participants.
Is a fix still possible?
Eskom has a fair case for wanting partners with proven scale. Eskom Green must be investable, and lenders want experienced sponsors. But capability at scale can be proven without excluding an entire domestic industry.
Clarification questions close on 30 November 2026, and responses on 12 January 2027. There is still time for Eskom to:
Eskom Green is meant to strengthen South Africa’s engineering, manufacturing and infrastructure development capacity. Building it on rules misaligned with government policy that push aside the country’s own developers after the same mistake on transmission would be an own goal that South Africa can ill afford.
Author: Chris Yelland – MD – EE Business Intelligence
Chris is an internationally respected energy analyst, consultant and electrical engineer. He is considered an expert on the South African energy market. This article was originally published by EE Business Intelligence and republished with permission.
Disclaimer: The articles and videos expressed in this publication are those of the authors. They do not purport to reflect the opinions or views of Green Building Africa, our staff or our advertisers. The designations employed in this publication and the presentation of material therein do not imply the expression of any opinion whatsoever on the part Green Building Africa concerning the legal status of any country, area or territory or of its authorities.
November 14, 2026
October 12, 2026
October 18, 2026
October 30, 2026
November 4, 2026
October 10, 2026
Disclaimer | Privacy Policy | Terms & Conditions | Returns Policy | Intellectual Property | Cookie Policy
© 2019 – 2026 GBA Digital Media Group. All Rights Reserved
Website Design | Website Maintenance ![]()
Subscribe to our weekly Top 5 Stories
"*" indicates required fields
You must be logged in to post a comment.