Jakarta, 19 November 2026 – Solar energy development is one of Indonesia’s strategies to reduce its dependence on fossil fuels, whose prices are vulnerable to geopolitical conflicts, while also cutting greenhouse gas emissions. With a technical solar energy potential exceeding 3.2 TW, Indonesia has significant opportunities to expand solar energy deployment. However, accelerating the development of solar photovoltaic (PV) power plants requires regulatory certainty, grid readiness, and growing electricity demand. 
These issues were highlighted during the launch of the Indonesia Solar Energy Outlook (ISEO) 2027 and the policy brief Sun on Water: Recommendations for Scaling Up the Deployment of Floating Solar PV in Indonesia, organized by the Institute for Essential Services Reform (IESR) on Wednesday (18 November 2026). 
Fabby Tumiwa, Chief Executive Officer of IESR, revealed that Indonesia’s installed solar PV capacity reached 1.59 GWp in the first quarter of 2026. Rooftop solar PV accounted for the largest share at 0.9 GWp, followed by utility-scale solar PV at 0.33 GWp. 
“Rooftop solar PV has grown organically without government incentives. Even with the quota system in place, industries and communities have continued to move forward on their own,” said Fabby. 
He urged the government to stimulate new electricity demand and ease rooftop solar PV quota restrictions, allowing households and industries greater flexibility to harness solar energy. 
Erick Ta’dung, Coordinator for Renewable Energy Business Development and Supervision at the Directorate of New and Renewable Energy and Energy Conservation, Ministry of Energy and Mineral Resources (MEMR), stated that the government is finalizing a draft Presidential Regulation on the 100 GWp Solar PV Program following its harmonization with relevant ministries and agencies. 
In parallel, the government is preparing revisions to Presidential Regulation No. 112 of 2022. Under the proposed regulatory framework, provisions governing solar energy will be regulated separately through the Presidential Regulation on the 100 GWp Solar PV Program. 
As an initial step toward achieving the 100 GWp target by 2029, the government has identified solar PV projects with a combined capacity of approximately 5.3 GWp. However, Erick acknowledged that their development continues to face challenges related to permitting, land use, and spatial planning, including overlaps with protected agricultural land and forest areas. 
To address these barriers, MEMR is strengthening coordination with the Ministry of Agrarian Affairs and Spatial Planning/National Land Agency (ATR/BPN), the Ministry of Forestry, and local governments to clarify land status and accelerate permitting processes. 
Aryeshah Akbar, Power System Modeler and Analyst at IESR and an author of ISEO 2027, highlighted the gap between announced projects and their readiness for implementation. Of the approximately 5.3 GWp of projects in the initial phase, only 526 MWp have specified commercial operation date (COD) targets. Around 4.2 GWp are ready for tender, while 441 MWp are under construction. 
“The challenge is how to turn announced projects into bankable, construction-ready projects through efficient tendering processes and certainty over land availability and grid interconnection,” Aryeshah explained. 
Similar challenges affect floating solar PV development. His Muhammad Bintang, Head of Electricity and Energy Storage at IESR, presented findings from IESR’s Sun on Water policy brief, which identified 42.5 GW of economically viable floating solar PV potential across 143 sites. However, deployment remains constrained by uncertainty over access to water bodies and complex permitting processes involving multiple authorities. 
Drawing on practices in China and Singapore, Bintang recommended establishing a national database of suitable floating solar PV sites. This database could be integrated into the Electricity Supply Business Plan or the implementation framework for the 100 GWp Solar PV Program to accelerate project preparation. 
From a developer’s perspective, Kuswara Harjowiyono, President Director of PT PLN Nusantara Renewables, reported that construction of the 133 MWp Karangkates floating solar PV project has reached 80% completion. According to Kuswara, physical construction can progress relatively quickly, while permitting and the resolution of social issues often take considerably longer. 
“We began developing the Karangkates floating solar PV project after receiving a letter of intent from PLN in August 2023. The power purchase agreement (PPA) was only signed in January 2024. One challenge that has not been sufficiently anticipated is the social dimension of reservoir utilization,” Kuswara explained. 
Anticipating Growth in Electricity Demand 
Beyond project certainty, electricity demand readiness emerged as another key issue during the discussion. Juniko Parhusip, Coordinator of the Electricity Working Group for Downstream Industrialization and Economic Zones at MEMR’s Directorate General of Electricity, noted that the growth of data centers could generate new electricity demand to support solar PV development in Indonesia. 
Zainal Arifin, Director of the Center for Energy Transition and Sustainability at PLN Institute of Technology, emphasized that additional generation capacity must be matched by the power system’s ability to utilize the electricity produced. Assuming a capacity factor of 16%, a 100 GWp solar PV fleet could generate approximately 140 TWh of electricity annually. 
Zainal estimated that absorbing this additional generation entirely through increased electricity consumption over three years would require annual electricity demand growth of approximately 12.74%, significantly higher than the average growth rate of 4.7% recorded in recent years. 
“The challenge is not simply building generation capacity. We must ensure that the 140 TWh of electricity can actually be utilized,” Zainal said. 
Addressing infrastructure requirements, Fandi Gunawan Sianipar, Manager of Various Energy IPP at PT PLN (Persero), explained that grid expansion to industrial estates must be aligned with electricity demand growth. New requirements not yet included in the RUPTL can be proposed through an RUPTL supplement mechanism to provide a basis for PLN’s infrastructure development. 
Raditya Wiranegara, Director of Research and Innovation at IESR, emphasized that rooftop solar PV deployment would not place an additional burden on public finances, as households and businesses contribute directly to its development. At the same time, wider rooftop solar PV adoption would increase the share of renewable energy in Indonesia’s electricity mix. 
Share on :
Jl. Tebet Timur Dalam Raya No.109 B-D, RT.5/RW.6, East Tebet, Tebet, South Jakarta City, Jakarta 12820
 
 [email protected]
 +62 21 22323069
 +62 21 22323069
Press Release
Contact Us
Careers
Request for Proposal
Privacy Policy
Internal
Indonesia Energy Transition Outlook
Indonesia Energy Transition Dialogue

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply