The national planning body has refused permission for a 120-hectare solar farm in North Kerry over a potential flood risk.
Kerry County Council had refused planning for Statkraft Ireland Ltd to install the solar panels across 43 farms between Listowel and Ballylongford.
The application site was across 120 hectares in the townlands of Ballyline West, Coolkeragh, and Kilgarvan, on both sides of the R552 between Listowel and Ballylongford.
When the company was refused planning by Kerry County Council, it appealed this to An Coimisiún Pleanála, which has also ruled against the solar farm.
The company said in its appeal that the development was designed to ensure it would operate safely during a flood, does not increase flood risk, and is an improvement compared to the current drainage.
The planning body sided with the company on some aspects of the original refusal, and acknowledged the visual impact would be acceptable, and there would be no significant impacts on the natural habitats on site.
The inspector also wrote that eight observations were submitted by local residents during the appeal process, all outlining objections to the solar farm development.
An Coimisiún Pleanála concluded that it was not demonstrated that surface water drainage and flood risk were adequately addressed, and it refused planning permission.
RadioKerry Newsletter
Sign up now to keep up to date with the latest news.
Processing your request…
You are subscribed now! please check your email to confirm your subscription.

Download RadioKerry App Today
Copyright © 2026 Raidio Ciarrai Teoranta. Developed by Square1 and Powered by PublisherPlus

source

This entry was posted in Renewables. Bookmark the permalink.

Leave a Reply