JNNSM: Phase 1 Batch 1, project status and tariff reduction numbers

 

Scheme
Projects allotted
Projects Commissioned
Weighted Average bid tariff
% Reduction in tariff
No.
MW
No.
MW
Large PV projects through NVVN
30
150
26
130
12.16
Rs. / Unit
32 %
2 Projects Cancelled
Migration Scheme
SPV
13
54
11
48
ST
3
30
1
2.5
RPSSGP Scheme (PV)
78
98
67
85.8
Solar Thermal projects through NVVN
7
470
Scheduled for  commissioning by May 2013
11.48          Rs. / Unit
25 %
Total
131
802
102
266.3

 

 

Unknown's avatar

About Ritesh Pothan

Ritesh Pothan, is an accomplished speaker and visionary in the Solar Energy space in India. Ritesh is from an Engineering Background with a Master’s Degree in Technology and had spent more than a decade as the Infrastructure Head for a public limited company with the last 9 years dedicated to Solar and Renewable Energy. He also runs the 2 largest India focused renewable energy groups on LinkedIn - Solar - India and Renewables - India
This entry was posted in JNNSM, PV, Renewables, Solar, Solar Thermal and tagged , , , , , , , , , , , , . Bookmark the permalink.

2 Responses to JNNSM: Phase 1 Batch 1, project status and tariff reduction numbers

  1. Pingback: A report on Rooftop Solar PV in India – Potential and Possible Solutions | Natural Group

  2. Pingback: Grid-connected rooftop and off-grid solar to get greater push in JNNSM Phase II | Natural Group

Comments are closed.