Off Grid SPV : Physical Targets and Achievements (Target: 200 MW in Phase-I) June 2012

   Year Target in MW Project Sanctioned (MW) Projects Installed(MW) 2010-11 32 40.65 10.79 2011-12 68 77.40 20.2 2012-13 100 Under progress Solar Thermal : Achievements §5.73 million square meter of solar thermal collector area installed so far cumulatively against … Continue reading

Posted in JNNSM, PV, Renewables, Solar, Solar Thermal | Tagged , , , , , ,

Solar Capacity requirement for Captive Compliance Requirement

  Company Name Captive Power Capacity (MW) Solar Capacity Required  for solar RPO compliance (MW) in 2012-13 J.K. Lakshmi Cement Ltd. 93.00 3.00 Indian Petrochemical Company Ltd. 257.00 3.40 Bharat Petroleum Corporation Ltd. 189.00 4.00 Wardha Power Company Ltd. 405.00 … Continue reading

Posted in PV, Renewables, Solar | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , | 1 Comment

Network of Solar Radiation Monitoring Stations in India

Posted in PV, Renewables, Solar, Solar Thermal | Tagged , , ,

Solar exemptions on tax, for those looking to import

Vide Custom Notification No. 25/1999 dated 28th February, 1999 there was no customs & Excise duty on cells and modules but some raw materials required to manufacture cells and modules attract 5% customs duty and CVD. Vide Custom Notification No. … Continue reading