| Scheme | Projects allotted | Minimum bid tariff | Maximum bid tariff | Weighted Average bid tariff | % Reduction in tariff | |
| No. | MW | |||||
| Large PV projects through NVVN | 28 | 350 | 7.49 | 9.44 | 8.77 | 43% |
| Rs. / Unit | Rs. / Unit | Rs. / Unit | ||||
Commissioning Date: Feb 2013, none commissioned yet