No. 29/5/2012-13/JNNSNM
Government of India
Ministry of New and Renewable Energy
Solar Power Division
Dated: 4/10/2013
Reference Draft Guidelines for setting up of 750 MW Grid Solar PV power projects with Viability Gap Funding under JNNSM, Ph-II, B-1 hosted on this Ministry’s website on 18/4/2013. The Ministry is thankful to all the stakeholders for their valuable comments.
2. A revised draft based on inputs received and broad framework of the VGF scheme approved by Government is attached. Comments, if any, on these guidelines may please be sent to the undersigned latest by 10/10/2013. The final Guidelines will be published on MNRE website soon thereafter and will form an integral part of the RfS/ Bid Document for the projects to be issued by the Solar Energy Corporation of India (SECI).
A. K. Varshney
Director (Solar Power)
Tel/Fax: 011-24360885
E-mail: akvarshney@nic.in
Pingback: Standard PPA and VGF Securitization Agreement for JNNSM Phase II Batch I | Natural Group