Daily Archives: February 24, 2016

Solar tariff trend in India from 2010-2016

Trend of Solar Tariff Previous bid results     Year Capacity on Offer (MW)   Highest Bid (Rs./KWh)   Lowest (Rs./KWh)   Weighted Avg. Price (Rs./KWh) NSM Batch 1 Dec’10 150 12.76 10.95 12.16 NSM Batch2 Dec’11 350 9.39 7.49 … Continue reading

Posted in Batch I, Batch II, Government, JNNSM, Phase I, Phase II, Power Generation, PV, Renewables, Solar, Solar Parks, Tranche I | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , | Leave a comment

Commissioning Status of Grid Connected Solar Power Projects under JNNSM in 2015-16

Commissioned in 2015-16 as on 31/01/2016 Commissioning Status of Grid Connected Solar Power Projects under JNNSM in 2015-16   Sr. No.     State/UT Total MNRE Projects MW   State Policy MW   RPO MW   REC Scheme MW Pvt. … Continue reading

Posted in Government, Grid Connected, Grid Interactive Distributed Solar Energy Systems, India, Karnataka, Madhya Pradesh, Maharashtra, New Delhi, Power Generation, Punjab, PV, Rajasthan, Renewables, Solar, Telangana, Uttar Pradesh | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , | Leave a comment

Commissioning Status of Grid Connected Solar Power Projects as on 31 Jan 2016

Cumulative Commissioned as on 31-01-2016  Commissioning Status of Grid Connected Solar Power Projects     Sr. No.     State/UT   Total MNRE Projects MW   State Policy MW     RPO MW   REC Scheme MW   Pvt. Initiative … Continue reading

Posted in Andhra Pradesh, Bihar, Government, Grid Interactive Distributed Solar Energy Systems, Gujarat, Haryana, India, JNNSM, Karnataka, Madhya Pradesh, Maharashtra, Ministry of Power, MNRE, New Delhi, Power Generation, Punjab, PV, Rajasthan, Renewables, Solar, Solar PV, Telangana, Uttar Pradesh | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , | Leave a comment